Connect Gamification Components to Real Data #148

Closed
opened 2026-03-26 09:12:49 +01:00 by kincses · 1 comment
Owner

Objective: Connect gamification components (leaderboards, badges, trophies) to real backend APIs instead of mock data.

Target Files:

  • Frontend: (all components)
  • Frontend store:
  • Backend: or similar
  • Database: tables

Acceptance Criteria:

  1. Leaderboard shows real user rankings based on actual points
  2. Badges unlock based on real user achievements
  3. Trophy cabinet displays earned trophies from database
  4. All gamification data comes from real APIs, not mock data

Execution Steps:

  1. Check existing gamification endpoints and data models
  2. Update frontend components to call real endpoints
  3. Implement achievement calculation logic if needed
  4. Test with real user data
  5. Ensure real-time updates work (when points change)

Technical Details:

  • Estimated effort: 2 days
  • Dependencies: Phase 1 completion
  • Priority: P1 (enables engagement features)
**Objective:** Connect gamification components (leaderboards, badges, trophies) to real backend APIs instead of mock data. **Target Files:** - Frontend: (all components) - Frontend store: - Backend: or similar - Database: tables **Acceptance Criteria:** 1. Leaderboard shows real user rankings based on actual points 2. Badges unlock based on real user achievements 3. Trophy cabinet displays earned trophies from database 4. All gamification data comes from real APIs, not mock data **Execution Steps:** 1. Check existing gamification endpoints and data models 2. Update frontend components to call real endpoints 3. Implement achievement calculation logic if needed 4. Test with real user data 5. Ensure real-time updates work (when points change) **Technical Details:** - Estimated effort: 2 days - Dependencies: Phase 1 completion - Priority: P1 (enables engagement features)
kincses added this to the Phase 2: Dashboard & Analytics Wiring milestone 2026-03-26 09:12:49 +01:00
kincses added the Status: To DoScope: BackendScope: FrontendType: Feature labels 2026-03-26 09:12:49 +01:00
kincses added Status: Done and removed Status: To Do labels 2026-06-18 02:19:30 +02:00
Author
Owner

Munka befejezve: 2026-06-18 02:19:30

Technikai Összefoglaló:
Closed via architectural refactoring and UI polish. Gamification components connected to real data. GamificationService expanded, points/badges/leaderboard operational with real database backend.

⏱️ Az idő rögzítve.

✅ **Munka befejezve:** 2026-06-18 02:19:30 **Technikai Összefoglaló:** Closed via architectural refactoring and UI polish. Gamification components connected to real data. GamificationService expanded, points/badges/leaderboard operational with real database backend. ⏱️ *Az idő rögzítve.*
Sign in to join this conversation.